The Transmission Company of Nigeria says its contractors are working tirelessly to erect four new transmission towers along the Jos-Gombe axis.
The company said this is to enable it to restore power supply to states in the North Eastern part of the country.
Ndidi Mbah, TCN’S General Manager, Public Affairs, stated this in a statement in Abuja on Friday.
Mbah said the erection of the towers followed an earlier destructive attack on four transmission towers by vandals.
She said that the towers collapsed and affected Gombe, Damaturu, Maiduguri, Yola, Bauchi and Jalingo.
She said: “Immediately after the incident, TCN’s engineers worked first to redistribute available bulk supply on the Jos-Bauchi-Gombe 132 KiloVolt (kV) line between Jos and Yola Discos.
”While work commenced immediately at reconstructing the four vandalised towers.
“Presently, we are rebuilding the four towers simultaneously.
“Progress is evident, with one tower nearing 80 percent completion and another at 60 per cent.”
According to her, the third is at 30 percent and dismantling work finished on the fourth tower.
Mbah said that additionally, tower members are being fabricated and assembled on-site to expedite construction.
She said that the company was committed to the quick restoration of bulk power on the line route.
She added: “Construction work on the Jos-Gombe transmission line, taking supply up to Damaturu and environs, will be completed and energised by May 20 while the Damaturu-Maiduguri axis will be completed on May 27.
“Expectedly, bulk power transmission will be fully restored on the affected 330kV transmission line by May 27, Yola and Jos DisCos will also be able to offtake and distribute optimally from TCN substations.
“For now, only 38 Megawatts (MW) is wheeled to both Jos and Yola Distribution companies, with each receiving 19MW each.”